New momentum for Indonesia’s stalled Masela gas field

Arifin Tasrif, the minister of energy and mineral resources for Indonesia, made reference to using hybrid offshore and onshore development systems in the Masela liquified natural gas ( LNG ) project, which has sparked rumors that plans to build a 170-kilometer pipeline across an undersea trench that is 3, 000 meters deep may be postponed or completely abandoned.

With a final purchase decision expected in the middle of 2026, at least seven years behind plan, majority Chinese client Inpex Corporation is speeding up construction on the 9.5 million kilogram per season Abadi LNG plant in rural Arafua Sea. & nbsp,

Since Indonesian and Malaysian state oil companies Pertamina and Petronas recently teamed up to purchase the 35 % stake in the project previously held by Royal Dutch Shell, one of the world’s pioneers of floating LNG technology ( FLNG ), the 13 trillion cubic feet ( TCF) project has gained some momentum.

Shell finally left Masela after the then-newly-installed government insisted in 2015 that it be converted from an offshore to an inland operation on the Tanimbar archipelago, which are located northwest of the Indonesia-Australian maritime border.

The Pertamina / Petronas consortium will pay an additional$ 375 million at the time of the final investment decision, and the US$ 650 million investment transaction will be settled in two payment tranches of$ 325 million in cash.

Then, based on the advantages he insisted it would bring to a small archipelago — andnbsp, now an occasional cruiser liner destination— as well as the rest of Maluku province to the north, chief maritime minister Rizal Ramli persuaded Widodok to switch to an onshore development.

In comparison to what the seaward solution might offer in terms of supplying gas directly from an FLNG to a string of power stations across uninhabited eastern Indonesia, some in-depth studies appear to have been conducted to reveal those benefits.

At this point, it is still unknown whether natural gas will be used to force the new LNG herb and how many of the 10, 000 Abadi workers may come from Maluku, an underdeveloped region of eastern Indonesia where copper has recently boosted economic growth. & nbsp,

According to experts, the Masela project’s now-planned use of a hybrid type of floating LNG concept that uses at least one 170, 000 cubic meter Floating Storage Regasification unit ( FSRU ) suggests that it may fill an anticipated supply gap before the pipeline is finished.

Given the challenges facing the tunnel, which runs along the western and southern coastlines of Sumatra and Java and is one of the busiest fault lines in the world, some analysts also wonder if the pipeline will even be built under the new government that will be installed in 2024.

Facebook’s image

A minimum of 80 % of an FSRU may be constructed at factories in China, South Korea, or Singapore, leaving small work for local businesses, including state-owned businesses that have benefited from numerous state construction deals over the past ten years. & nbsp,

The only two FSRUs already operating in Indonesia are used for upstream supply to LNG-run power plants, not for downstream projects, in Jakarta Bay and off the southern Indonesian province of Lampung.

An inland facility, according to critics, would benefit politically connected business interests in Jakarta who are either suspected of buying real estate on Yamdena’s primary Tanimbar island or who stand to win lucrative work contracts for the project. & nbsp,

The LNG service may be constructed on a 600-hectare site on Yamdena, which is 3, 000 square kilometers in size and home to 123, 000 mostly Christian residents who work as subsistence farmers or fishermen.

After the Ichthys LNG job on the Northwest Shelf of Western Australia, where the business is considering building a second generation educate at its 8.9 million tonnes per year LNG facility, Masela will overtake Inpex as its second-largest management asset.

Takayuki Ueda, the CEO of Inpex, stated last month that a revised Plan of Development ( POD) would be approved by Indonesian authorities thanks to letters of intent the company had with potential LNG customers.

Inpex and Shell originally intended to mark the POD at the G20 Summit in Osaka, Japan, in 2019, but it was already obvious that the British foreign was leaving after the government changed its mind.

The Masela plant will also include carbon capture, utilization, and storage ( CCUS ) technology, which is anticipated to cost an additional$ 1.2 to$ 1.4 billion, in addition to & nbsp, The & NBSP, FSRU.

For the state power utility Perusahaan Listrik Negara’s( PLN) network of six sizable LNG-fired facilities, which contribute roughly 8, 000MW of the 53,000MW major Java-Bali network, the use of CCUS technology is in line with the government program for the transition to clean energy.

Natural gas, which is still a fossil fuel, will eventually replace coal with renewable energy sources like geothermal, renewable, and wind because they are still in the early stages of development and don’t easily lend themselves to trusted baseload power.

More than 70 % of the Java-Bali network is still dominated by coal and nbsp from Sumatra and Kalimantan. With installed solar capacity of only 300 MW, only 7.7 % of gridrelies are powered by renewable sources, primarily geothermal and water.

Experts claim that while regular inland LNG terminals, of which Indonesia now has three also operational, require extensive berthing, piping, storage tanks, and associated infrastructure, the FSRUs do not.

According to one Jakarta-based oil and gas expert with extensive expertise in Indonesia’s rich gas fields, the more recent integration of an FSRU into downstream gas projects may offer a number of benefits.

It’s crucial to remember that careful planning and taking technological, economic, and regulatory factors into account when using an FSRU upstream. To ensure effective and secure gas handling and storage,” their inclusion involves designing appropriate connections, safety measures, and procedures.”

An FSRU can be used among its inland applications to temporarily store extra gas produced during high generation times, preventing waste and enabling controlled distribution as production rates fall.

Additionally, the associated fuel can be collected and stored, therefore re-gasified and used for energy generation or other reasons, eliminating the need for gas flaring by connecting an FSRU to an inland LNG facility.

To overcome difficulties in constructing long-term inland system, inland fuel projects in isolated or commercially residual locations, such as Masela, could also use an FSRU. It may be a cost-effective method of storing the gas in these situations before it is delivered to consumers or larger pipes.

An FSRU may be quickly deployed to meet small project deadlines and take advantage of beneficial market conditions, experts point out, because standard inland gas processing facilities may take several years to plan, design, and construct.

An FSRU may act as a temporary LNG professional end if the inland project is close to the coast, allowing the gas to be liquefied and stored it before being sent to large LNG carriers for export.

Since its inauguration on July 26, the Masela project has made progress as BP’s long-delayed third Tangguh production train in West Papua ramps & nbsp, up production, and it is now the largest LNG processor in the nation, surpassing Kalimantan ‘ 45-year-old Bontang plant.

A BP spokeswoman predicts that the first LNG will be fully functional by the end of the year, essentially doubling Indonesia’s LNG manufacturing to 30.5 million tonnes by 2027 and giving the sector a new lease on life. It left the next teach on September 13.

PLN, which intends to change many of its outdated coal-fired power stations with oil and, to a lesser extent, renewable energy by 2040, will receive about 75 % of the creation. & nbsp,

The Geng prospect, which was first discovered by Indonesian junior Black Platinum in the North Ganal production sharing contract( PSC ) block 85 kilometers off East Kalimantan in 2011, revealed 500 billion cubic feet of gas and 400 million barrels( MMBLS ) of associated condensate, according to recent announcements from Italian major ENI.

In its quest to achieve net zero, Indonesia wants to use more natural oil in its energy mix. Image: Facebook

North Ganal, the third-largest discovery in the Kutai Basin, is to the south of the Indonesia Deepwater Development ( IDD ) project, which was recently purchased from Chevron — the most recent US oil major to leave Indonesia — and will now make IDD a much more alluring business proposition.

Through a mutual research with ENI, Black Platinum activated the North Ganal wall, and the Roman company joined forces with them in 2011. The Italians first had no interest in Geng and decided to practise what ultimately proved to be a remote possibility in 2012.

Eni suddenly acquired 62 % of the administration right to five oil fields in the Makassar Strait that were previously owned by Chevron. IDD working areas are currently being integrated into North Ganal, and future production is assisting in reducing the potential supply uncertainty of local Bontang.